News: Jardines I y Jardines II - Fence Replacement
Dear owners,
Please be informed that on the 8th May work will commence to replace the current wooden fencing with the recycled plastic fencing approved at the 2023 Annual General Meeting, at Jardines I and Jardines II swimming pools, according to the timetable shown on the table below:
Pool |
Start Date |
End Date |
J4 |
08/05/2023 |
12/05/2023 |
J5 |
15/05/2023 |
19/05/2023 |
J7 |
22/05/2023 |
26/05/2023 |
J9 |
29/05/2023 |
02/06/2023 |
J10 |
05/06/2023 |
09/06/2023 |
J11 |
12/06/2023 |
16/06/2023 |
J13 |
19/06/2023 |
23/06/2023 |
The material is scheduled to be stockpiled in Garden 4 and Garden 5 on Friday 5 May. In the event that this does not take place tomorrow, it will be done on Monday 8 May before work commences.
The parking spaces where the removed wooden fencing is to be deposited and which the company in charge of the works will use for storage have been marked and cordoned off. The locations of these parking spaces are shown in the attached presentation, so please refrain from parking there for the duration of the works.
Thank you in advance for your attention and cooperation.
We apologise for any inconvenience caused.
Yours faithfully