Why is the Painting taking so long? - The painting was agreed to be paid for over 4 years at the AGM in 2016. We have paid almost 3 years (2016, 2017 & 2018) with 1 years remaining 2019. Once these payments are complete everyone would have paid they agreed amount.
Why is my property not painted yet? - Of course there will be areas that are not painted at the moment. We have 2 years remaining and we can only paint as money is received.
Has the painting stopped? On the 5th April 2018 we re-started with the painting (starting with Penthouses 15& 16) and all remaining properties will be painted over the following year and La Isla in 2020
What is the Painting Procedure ?
-Cleaning. Wire brush/abrasive pad (no pressure washing as this introduces moisture in to wall surface and invalidates the warranty)
-Fixative on ledges.
-1st coat of paint mixed with fixative as instructed by the paint manufacturer, Pinturas Pinay.
-2nd direct coat as instructed by the paint manufacturer
The 2nd coat of paint is applied once the 1st is dry. Which has to be a day later
So on the first day, the 1st coat with fixative, and on the next day, the 2nd (finishing) coat.
The planned schedule is:
Garden |
START |
JARDIN 9 |
05/2018 |
JARDIN 7 |
09/2018 |
JARDIN 4 |
11/2018 |
JARDIN 5 |
12/2018 |
JARDIN 8 |
02/2019 |
JARDIN 10 |
March 15th to April 14th |
NARANJOS 1 |
April 15th to April 30th |
NARANJOS 2 |
May 1st to May 30th |
NARANJOS 3 |
June 1st to June. 25th |
NARANJOS 4 |
09/2019 |
NARANJOS 5 |
10/2019 |
NARANJOS 6 |
11/2019 |
La Isla |
01/2020 |
All Dates are approximate |
What was presented at the 2016 AGM? Click the file below for the information which was included in the 2016 AGM explaining the painting inclusions.I want to cancel my painting payments - If you cancel your payments towards the painting before they are complete, this will put you in to debt with the community and treated as any other debtors. You will loose your payment discount.Click here for latest painting update