Dear owners,

As you are aware the initial work on the voids on N7 and N8 was completed in July.

We are now continuing the work. During the time the work is undertaken on your block you will need to expect some noise while they are drilling through the building block. The noise might last for 3-4 weeks on and off.

The schedule is as follows:

N7: Block 1 Will be started the 4th of November. Apartment number 585 – 608 estimated completion date first week of December 2024 (5 units)

N8: Block 1 Apartment number 725 - 748 estimated completion date last week of December 2024 (4 units)

N7: Block 8 Apartment number 609 – 616 estimated completion date end week of January 2024 (5 units)

N7: Block 7 apartment number 617 - 640 estimated completion date first week of February 2025 (3 units)

N7: Block 6 Apartment number 641 – 664 estimated completion date mid-February 2025 (5 units)

Apologies for any inconvenience caused.

Kind regards.